Critics of two data centre projects in Beringen, a municipality in the canton of Schaffhausen, have formed an association to oppose them. The group says the facilities’ resource use is a concern, SRF reports.

About 40 people attended a meeting at the Gaswerk site in Schaffhausen. One participant told SRF that residents had a right to be consulted, while another said the centres’ electricity, water and overall resource consumption remained unclear.

One data centre is under construction in Beringen after a building application was filed five years ago. A second project, planned by Turkish company Enka, is well advanced in the planning process. The facility under construction is being developed by US company Stack Infrastructure.

At full capacity, the two centres would raise annual electricity use across the canton from 470 to 1,135 gigawatt-hours, an increase of 140 per cent. The electricity would be purchased internationally. The facilities would also require 85 million litres of water a year for cooling, increasing Beringen’s water demand by up to 15 per cent.

Eva Neumann, a Social Democratic Party member of the Schaffhausen cantonal parliament and a board member of the new association, said she could see no positive aspects to the centres and was concerned about resource use. She also questioned plans to use their waste heat, saying Beringen, which has 5,500 residents, does not have infrastructure for a district heating network.

Beringen mayor Roger Paillard of the Free Democratic Party said the municipality recognised residents’ concerns, but the centres could bring tax revenue and jobs. He said the municipality had limited influence over electricity use, but had secured an agreement for one centre to use rainwater. Discussions with the operators were ongoing, with a focus on using waste heat.

The association is calling for a temporary halt to construction. The Schaffhausen government has tightened rules setting limits on data centres’ electricity and water use and greenhouse gas emissions. The rules take effect on December 1, 2026. The cantonal parliament is expected to discuss further tightening them in mid-December.