Carinthian communities challenge finalized 380-kV power line route
Tuesday 24th November 2026 on 20:30 in
Austria
Communities affected by the planned 380-kilovolt power line through Carinthia continue to oppose its finalized route, criticizing both the path and what they describe as a lack of communication from Austrian transmission operator Austrian Power Grid (APG), ORF reports.
APG presented the detailed route on Monday. It runs 193 kilometres from Lienz in East Tyrol across Carinthia to the Obersielach substation east of Völkermarkt, and is planned to include 670 pylons. APG is responsible for Austria’s nationwide electricity transmission network and is wholly owned by Verbund, which is majority-owned by the Republic of Austria.
In Sachsenburg, four landowners and the mayor object to a planned pylon on land south of Möllbrücke railway station. They say it was not on the earlier, broad route plan, which they understood would follow an existing 110-kilovolt line.
Sachsenburg Mayor Wilfried Pichler called the detailed route a “catastrophe” for the municipality and nearby Lurnfeld. He said it would cross the Möllbrücke industrial area and the Drau cycle path, as well as the L14 road used by children travelling to the school centre and railway station. Pichler said the municipality would use all available legal options.
Landowner spokesman Christoph Lampersberger said the route would completely devalue two hectares of potential commercial land, currently used as farmland. He also questioned whether electricity consumption should continue in its current form.
Opposition has also formed in Treffen. Arnulf Dobernig, a spokesman for a local citizens’ initiative, said APG had considered only some of the suggestions put forward. He objected to the route passing over the municipality’s largest shopping centre and close to a forest kindergarten, and said it remained too close to homes.
Johann Huber, spokesman for the Landskron citizens’ initiative, said residents living near the route and owners of land where pylons are planned had not been contacted. The group plans to submit objections if the route reaches the approval stage.
Treffen Mayor Christof Seymann said the municipality had not approved the project. He said several meetings and an on-site inspection had taken place, but promised further meetings had not been held in the past two to three months.
Residents in Treffen and Sachsenburg are calling for more talks with APG and visualisations of the project. Some pylons are expected to reach 80 to 100 metres in height. APG has promised more information at public information events due to begin in individual municipalities.