A99 closure in Munich east as crews demolish ageing bridge

Saturday 21st November 2026 on 12:15 in Bavaria

A99, Munich, traffic closures

The A99 is closed between the Munich-East and Munich-South junctions while crews demolish a deteriorating bridge near Haar. The motorway is expected to reopen by 5am on Monday, BR reported.

The closure began on Friday evening. The bridge, built in 1973, has deteriorated faster than expected, and authorities say it must be removed and replaced to eliminate safety risks.

On Saturday morning, traffic on the A99 and in Munich remained calm, with no major tailbacks. Michael Kordon, head of the Autobahn GmbH’s southern Bavaria branch, said an information campaign had helped keep traffic well below normal levels.

Crews are using six excavators to break up the bridge and load the concrete into containers. The work must be completed in about 57 hours. The bridge is nearly 100 metres long and 31 metres wide, and machinery can operate from only one side because a temporary bridge has stood on the other side for several months.

The schedule is tight, and officials said there was still some uncertainty about how the demolition would proceed. The Autobahn GmbH advised drivers to avoid non-essential journeys in the greater Munich area, allow extra time or use public transport. Drivers coming from farther away were urged to consider alternative routes before reaching Munich.

Up to 100,000 vehicles normally use the Munich ring road each day. Authorities expect some drivers to take the Mittlerer Ring through the city or use smaller roads, potentially causing congestion in Munich and the districts of Munich, Ebersberg and Erding.

Source 
(via BR)