Inquiry says Rhône flood damage could have been prevented

Thursday 19th November 2026 on 12:01 in Switzerland

flood protection, Rhône, Valais

A parliamentary inquiry has concluded that flooding in Siders-Chippis in 2024 could likely have been avoided, citing years of failures by government departments and politicians. Swiss broadcaster SRF reported that the commission found no single person responsible, but identified a collective failure.

Heavy rain in late June 2024 caused the Rhône to overflow, flooding the industrial district of Siders-Chippis and the grounds of aluminium companies Constellium and Novelis. The damage ran into millions of francs.

The affected river stretch is part of the third Rhône correction, a flood-protection project that has been under way in the canton of Valais for more than 20 years. The project covers 162 kilometres of river and is intended to protect more than 100,000 people. It is estimated to cost about 3.6 billion francs.

The inquiry found that preparations for protection work in Siders-Chippis were inadequate. When plans were made public in 2008, many questions remained unresolved. An expert assessment cited by the commission said a flood there would very likely not have occurred if the project had been implemented.

Disputes among cantonal departments also stalled the work for years. A disagreement over protecting old industrial buildings and villas along the river blocked demolition needed to widen the riverbed.

The commission said political leadership failed to resolve the disputes. It credited former construction director Jacques Melly, who served from 2009 to 2021, with wanting to move the project forward, but said he did not overcome the departmental deadlock. Under his successor, Franz Ruppen, the project lost political priority from 2021, and urgent works remained effectively on hold until the 2024 floods.