Flood risk halts planned data centre in Stetten
Wednesday 18th November 2026 on 16:01 in
Austria
A planned data centre in Stetten, in the district of Korneuburg, has been called off for now because the proposed site is at risk of flooding, ORF reports. The project would have covered 4.3 hectares in the municipality’s commercial zone.
A new flood study by the Ministry of Water Management and Lower Austria’s water management department has found that the zone is vulnerable to flooding. The study, which has been available at the municipal office since Tuesday, examined the two most recent floods.
Mayor Thomas Windsor-Seifert (SPÖ) said water from the Danube could back up into the Donaugraben. Tributaries flowing into the channel would then be blocked, potentially flooding the commercial zone. The land is now classified as an HQ30 flood zone, meaning it could be inundated during a flood that occurs statistically once every 30 years. The required rezoning is therefore no longer possible.
Windsor-Seifert said the municipality had no alternative plots suitable for the project and would take no further action for now. The project’s initiator is seeking a technical solution. A citizens’ initiative had previously gathered thousands of signatures opposing the data centre. The mayor said he was not opposed to such a facility in principle, but it should not come at the expense of residents or nature.
Green Party planning spokesperson Georg Ecker called the cancellation good news for Stetten and Lower Austria, while criticising the choice of a site that is statistically flooded every 30 years. Another planned data centre, in Zistersdorf in the district of Gänserndorf, was recently abandoned after its investor became insolvent. That project was planned on a site of about 14 hectares.