Three Styrian towns connect district heating networks
Wednesday 25th November 2026 on 12:30 in
Austria
Three municipalities in eastern Styria have connected their district heating networks, enabling them to exchange 26 gigawatt-hours of heat, ORF reports. The 8.5-kilometre pipeline links Weiz, Wollsdorf and Gleisdorf, whose networks currently produce a combined 100 gigawatt-hours.
Laid since spring along the railway line between Wollsdorf and southern Weiz, the pipeline allows the municipalities to share heat generated from biomass and industrial waste heat.
The project aims to double the region’s fossil-free heat supply over the next five to 10 years. Project manager Joachim Kelz said the network was intended in particular to support the shift away from fossil fuels by industrial and commercial businesses along the route. Numerous industrial companies are already connected, he said.
The infrastructure cost 20 million euros. The partners are the Bioenergie Group, Fernwärme Weiz and Stadtwerke Gleisdorf. Gleisdorf Mayor Christoph Stark said households would also benefit from greater supply security. The town’s district heating network has been expanding for about five years and is due to grow further next year.
Heat currently comes from wood chips, with locally sourced timber used under long-term contracts with forestry businesses. The system also uses waste heat from the Gleisdorf wastewater treatment plant and solar thermal energy.
The project’s overall goal is to increase heat supply along the route to 200 gigawatt-hours. Additional industrial waste heat could help the network supply nearly 10,000 households a year within five to 10 years.