Crews demolish A99 bridge on schedule, reopening expected Monday

Sunday 22nd November 2026 on 18:30 in Bavaria

A99, Oberbayern, roadworks

Crews have demolished the ageing bridge over the A99, and the motorway is expected to reopen at 5 a.m. on Monday, BR reported. The demolition and clearance work have so far stayed on schedule.

The A99 has been closed in both directions between the Munich-South interchange and Munich-East since 8 p.m. on Friday. Crews first laid gravel over the road to protect the asphalt from falling pieces of the bridge. At times, eight excavators worked on the demolition.

About 50 to 60 people worked in shifts around the clock over the weekend. Traffic on the closed section was around a third of the level seen on comparable weekends, and the Autobahn GmbH said major traffic disruption had been avoided.

Workers are now sorting the bridge material. A large magnet is separating steel from concrete, and the Autobahn GmbH said almost all of it could be recycled.

Construction of a new bridge is due to begin immediately and is expected to take two years. Traffic will use a temporary bridge while the work is under way.

Source 
(via BR)