Arlberg railway line reopens after five-day maintenance closure
The Arlberg railway line between Ötztal and Bludenz will reopen to trains on Monday after five days of planned maintenance, ORF reported. The Austrian Federal Railways (ÖBB) completed 90 construction and maintenance projects during the closure.
About 120 workers carried out the work, in some cases around the clock and as snow began to fall. An 80-bus replacement service operated for passengers while the line was closed.
Work in Tyrol included replacing sections of track between Landeck and Pians, maintenance on tracks and switches using tamping machines, and cleaning several tunnels. Parts of several switches were also renewed at St Anton station. Workers carried out surveys and preparations for future construction projects.
A key focus was Schönwies railway station in the Landeck district, where work included changes to overhead lines and tracks, cable installation and commissioning a new electronic signalling system. The new system was connected to central control.
The station redevelopment began last year and is due to finish by the end of next year. The project includes renewing about two kilometres of track, five switches and the overhead line system, as well as building new platforms, an accessible underpass and updated passenger facilities.