Linz builds three-kilometre tunnel for district cooling

Friday 20th November 2026 on 17:30 in Austria

district cooling, infrastructure, Linz

Linz is building a roughly three-kilometre tunnel to supply district cooling to parts of the city centre, ORF reports. The tunnel, around 30 metres underground, is part of a LINZ AG project intended to cool buildings without adding heat to the city. The system is scheduled to start operating in mid-2028.

The tunnel will run between the Energiepark Linz Mitte, an energy facility on Nebingerstraße, and Rainerstraße. It will carry district-cooling pipes as well as electricity and fibre-optic cables. LINZ AG says the project responds to growing demand for cooling in cities.

About 900 metres of the eastern section have been completed. Construction is under way near the Design Center, where the tunnel’s launch shaft is located. The eastern section towards the energy facility is expected to be finished in early 2027, before work begins towards Rainerstraße. Tunnel excavation is scheduled to be completed in summer 2027.

The tunnel is being built using microtunnelling, with a machine operating underground and designed to cause minimal vibration. The machine was lowered into the roughly 30-metre-deep launch shaft in September. The tunnel is being built in sections in two directions.

Six shafts will provide access along the route. Three larger shafts will serve as starting or finishing points for the tunnel boring machine, with smaller access shafts between them. The tunnel will hold four district-cooling pipes, high- and medium-voltage lines, and telecommunications and fibre-optic cables. LINZ AG says bundling the infrastructure will protect it and make maintenance easier.

The tunnel lining will use about 1,000 reinforced-concrete pipe sections. Each section is just under three metres long and weighs about 22 tonnes.

The full district-cooling project is expected to cost around 100 million euros. The European Investment Bank has pledged LINZ AG a total of 200 million euros for climate-resilient infrastructure, part of which will go to the project. Linz Mayor Dietmar Prammer, who also chairs the LINZ AG supervisory board, described it as an investment in the city’s infrastructure and preparation for rising cooling demand in coming decades.

A district-cooling plant is being built at Energiepark Linz Mitte in parallel. LINZ AG says construction began in early July 2026. The plant and tunnel are both scheduled to be completed and operational by mid-2028.

Source 
(via ORF)